THIS IS AN INVITATION FOR BID, PLAN AND SPECIFICATIONS ARE AVAILABLE
Â
Full and Open Competition with HUBZone price preferenceÂ
PROJECT NUMBER: CA FTNP SEKI 13(2)Â
PROJECT NAME: MINERAL KING ROADÂ
PROJECT DESCRIPTION:Â
The project proposes to rehabilitate up to 12.09 miles of Mineral King Road located within Sequoia and Kings Canyon National Park (SEKI). The project is located east of Visalia in Tulare County, CA.Â
SCOPE OF THE WORK:Â
The scope includes pulverization of the existing pavement, aggregate base placement, and asphalt paving of the roadway. Parking lots will be rehabilitated or paved to improve visitor access. Soldier pile walls, soil nail walls, and areas of special rock embankment will be constructed throughout the project to stabilize the roadway. The project also includes drainage improvements such as ditch paving and grading, inlet installation, culvert replacement, and inlet and outlet protection measures.Â
The Mineral King Road Project is in remote mountainous terrain with areas of limited roadway bench width. Public access will have to be maintained during construction with intermittent allowable closures depending on season and time. The road is inaccessible during winter due to extreme weather and snowpack. The project is in an environmentally sensitive resource area within the National Park Service.Â
PRINCIPAL WORK ITEMS:Â
22,500 LF Ditch ExcavationÂ
1,900 CY Rip RapÂ
700 CY Special Rock EmbankmentÂ
6,500 Tons Roadway Aggregate, Method 2Â
7.5 Miles Full Depth Reclamation, Method 2Â
4.5 Miles Full Depth Reclamation, Method 2 with CementÂ
26,000 Tons Asphalt PavementÂ
380 LF Steel H Piles, In PlaceÂ
9,800 LF 24" to 48" CulvertsÂ
70 Each Inlet (Concrete Box Inlet)Â
37,000 LF Paved Ditch, AsphaltÂ
80 Each Dry Stacked HeadwallÂ
ANTICIPATED SCHEDULE:Â
Preshow Onsite Meeting - October 2024Â
Advertisement - October 2024Â
Construction - April 2025 through October 2027Â
Estimated Cost Range:Â $25M to $35M
- Opportunity closing date
- 06 November 2024
- Value of contract
- to be confirmed
About the buyer
- Address
- 6982AF CENTRAL FEDERAL LANDS DIVISI
The deadline to apply for this opportunity has passed.
Visit the
opportunities page
to find another.